The Public Utility Commission of Texas approved changes in the allocation factors used in the Transmission Cost Recovery Factors at Sharyland Utilities, LP, which are intended to bring a modicum of rate relief to residential customers.

Citing the unique circumstances of the case, and that its decision was non-precedential, the PUC approved a change in the TCRF rates based on the new allocation factors effective December 1, 2015, with new TCRF rates being charged to retail electric providers as of that date.

Typically, TCRF changes go into effect September 1 and March 1, but Commissioners stressed the need for the new rates to go into effect prior to the winter peak to bring meaningful relief to residential customers.

Commissioners declined to make the new TCRF rates based on the revised allocation factors retroactively effective back to September 1, 2015.

Though final tariffs have yet to be filed, based on Sharyland's June 1, 2015 filing to update the TCRF, here are the differences in the currently effective TCRFs versus what the TCRFs would have been (as originally filed), effective September 1, had the allocation factor changes been approved prior to the September 1, 2015 TCRF update (these may be subject to minor adjustments as were made to the current rates during the semi-annual TCRF review):

Currently Effective TCRFs

Residential              $0.017884 per kWh
Secondary ≤ 10 kW        $0.023936 per kWh
Secondary > 10 kW
   IDR                   $4.388575 per 4CP kW
   Non-IDR               $3.137608 per NCP kW
Primary
   IDR                   $4.201264 per 4CP kW
   Non-IDR               $0.398211 per NCP kW
Transmission             $4.035734 per 4CP kW
Lighting Service         $1.725786 per Light

Filed 9/1/15 TCRFs Had Allocation Factors Been Changed (Not Final)

Residential              $0.014566 per kWh
Secondary ≤ 10 kW        $0.019251 per kWh
Secondary > 10 kW
   IDR                   $4.383630 per 4CP kW
   Non-IDR               $2.562106 per NCP kW
Primary
   IDR                   $4.196529 per 4CP kW
   Non-IDR               $1.995102 per NCP kW
Transmission             $4.038733 per 4CP kW
Lighting Service         $0.670339 per Light

ADVERTISEMENT
NEW Jobs on RetailEnergyJobs.com:
NEW! -- Marketing/Channel Manager -- Retail Supplier -- Houston
NEW! -- Settlements Analyst -- Retail Supplier
NEW! -- Manager, Operations -- Retail Supplier -- Houston
NEW! -- Data Administrator -- Retail Supplier
NEW! -- Customer Support and Retention Rep -- Retail Supplier -- Houston
NEW! -- Contracts Analyst -- Retail Supplier -- Houston
NEW! -- Pricing Analyst -- Retail Supplier
NEW! -- Billing Analyst -- Retail Provider -- Houston
NEW! -- Energy Services Program Director - $230K
NEW! -- Senior Retail Analyst -- Retail Supplier
NEW! -- Manager, Retail Pricing -- Retail Provider
NEW! -- Retail Commodity Pricing Analyst -- Retail Supplier
NEW! -- Director of Pricing, Risk & Portfolio -- Retail Supplier
NEW! -- Manager/Director, Customer Retention and Satisfaction -- Retail Supplier -- Houston
NEW! -- Bilingual Rep Support Specialist -- Retail Supplier
NEW! -- Commercial Sales Support Analyst -- Retail Supplier -- Houston
NEW! -- Financial Analyst -- Retail Energy Supplier

Email This Story

HOME

Copyright 2010-15 Energy Choice Matters.  If you wish to share this story, please email or post the website link; unauthorized copying, retransmission, or republication prohibited.

 

Archive

Daily Email

Events

 

 

 

About/Contact

Search