ERCOT Finds Unit To Be Mothballed Not Needed For Transmission System Reliability
The following story is brought free of charge to readers by EC Infosystems, the exclusive EDI provider of EnergyChoiceMatters.com
Note: This story was first published on Jan. 17 with an alert to our email subscribers
ERCOT has issued a Reliability analysis determination for the City of Garland, Gibbons Creek Generating Station (GIBCRK_GIB_CRG1), given the Notification of Suspension of Operations submitted for the unit.
As previously reported, on December 21, 2018, ERCOT received a Notification of Suspension of Operations (NSO) for the following Generation Resource: City of Garland – GIBCRK_GIB_CRG1
The NSO had indicated that the Generation Resource will be mothballed indefinitely beginning June 1, 2019. Pursuant to a previous NSO filed on April 30, 2018, this Resource has been mothballed since October 1, 2018, and, under the April 30, 2018 NSO, was previously expected to be mothballed for a period of not less than 7 months and not greater than 8 months.
Pursuant to ERCOT Protocol Sections 3.14.1.2(4) and (5), ERCOT has completed its reliability analysis and has determined that this Generation Resource is not required to support ERCOT transmission system reliability and may suspend operations according to the schedule in the NSO.
ADVERTISEMENT Copyright 2010-16 Energy Choice Matters. If you wish to share this story, please
email or post the website link; unauthorized copying, retransmission, or republication
prohibited.
January 17, 2019
Email This Story
Copyright 2010-19 EnergyChoiceMatters.com
Reporting by Paul Ring • ring@energychoicematters.com
NEW Jobs on RetailEnergyJobs.com:
• NEW! -- Energy Sales Broker
• NEW! -- Business Development Manager -- Retail Supplier -- Houston
• NEW! -- Business Development Manager
• NEW! -- Regulatory & Compliance Analyst -- Retail Supplier
• NEW! -- Sales Quality & Training Manager -- Retail Energy
• NEW! -- Sales Analyst / Senior Level -- Retail Supplier
|
|
|