|
|
|
|
Draft Calif. Decision Would Determine Schedule For New Direct Access Load, Allocation To Wait List Customers
The following story is brought free of charge to readers by EC Infosystems, the exclusive EDI provider of EnergyChoiceMatters.com
The California PUC has issued a proposed decision which would address various facets of the statutory increase in direct access (DA) load of 4,000 gigawatt-hours
The proposed decision would apportion the new DA load over two years using the 2019 and 2020 waitlists. Under the draft, 2,000 GWh of the DA expansion would be enrolled pursuant to an expedited schedule, and the remaining 2,000 GWh would be enrolled using the 2020 waitlist.
The proposed decision would apportion the new DA load to the three large investor-owned utilities as follows (in kWh):
Existing Cap Expanded Cap
PG&E 9,520,000,000 11,393,225,285
SCE 11,710,000,000 13,456,866,759
SDG&E 3,562,000,000 3,941,907,956
The draft provides that, to accommodate resource adequacy (RA) planning requirements, the load that is enrolled pursuant to the 2019 Waitlist cannot begin DA service until January 1, 2020, and customers enrolled pursuant to the 2020 Waitlist cannot begin DA service until January 1, 2021.
The draft provides that, by June 14, 2019, the IOUs must notify customers who are on the
waitlist that is effective for 2019 and who are eligible to join the DA program they may
switch to the DA program. By July 8, 2019, the notified customers must state
whether they choose to switch from their current service provider to DA service. By July 31, 2019, customers who choose to switch to the DA program must
select an ESP and the ESP must submit the Direct Access Service Request (DASR)
form to the incumbent IOU.
"To be clear, to participate in the DA expansion
starting on January 1, 2020, each customer’s DASR form must be submitted to the
IOU by July 31, 2019," the draft states
To comply with provisions of SB 237, the draft would allow a one-time exception
from the requirement in D.18-06-030 that LSEs must submit the 2020 year-ahead
load forecast on April 16, 2019. Because the RA program allows LSEs to adjust
the 2020 year-ahead forecast in August and the DA expansion represents
approximately two percent of peak load, "we find that having the affected ESPs
reflect the DA expansion through the adjustment process is reasonable," the draft states
"However, all other requirements of D.18-06-030 remain in place, including
submittal of an August revised load forecast for 2020 that reflects migrating load
and compliance with 2020 year-ahead and month-ahead RA filing requirements," the draft states
In order to ensure that RA allocations are consistent with load migration
resulting from the DA expansion, ESPs gaining customers must provide
documentation with their August revised load forecasts that indicates which LSEs will be losing those customers, the draft states.
The 2020 Waitlist will be created by a lottery run in June 2019 for new service in January 2021. The deadline for participation on the 2020 Waitlist would be June 14, 2019
The draft would order that the IOUs must provide CCAs in their service territories with the amount of aggregated load for existing CCA customers who have elected to switch to the DA program.
The draft would find that the PCIA vintage that is assigned to CCA
customers should not change if that customer leaves CCA service to join the DA
program.
The draft would deny a proposal from the California Community Choice Association (CalCCA) to limit the amount of direct access within CCAs
As summarized in the proposed decision, "CalCCA argues that some CCA service territories that have six to
12 percent of load on the DA waitlist could 'face disparate impacts' as those
amounts 'represent a significant volumetric shift for already projected-and
procured for—load along with potential changes in overall load profile which
would impact procurement planning.' Further, CalCCA asserts, that unlike
IOUs, CCAs are not guaranteed cost recovery through mechanisms such as the
PCIA and the Cost Allocation Mechanism. To resolve this issue, CalCCA
requests that the Commission establish a cap on the amount of customer load
that is eligible to join the DA program (CCA Cap) and that the cap should be
based on the 'lesser of load currently on the existing waitlist or [the CCA’s] fair
share of load.'
The draft would find that, "CalCCA’s proposal would stifle customer choice
and provide preferential treatment to certain LSEs (CCAs) over IOUs and ESPs..."
The draft suggests that CCAs address direct access migration risky by, "revising their risk management plans or implementing mechanisms that are
similar to the regulatory framework established for the PCIA."
Rulemaking 19-03-009
ADVERTISEMENT Copyright 2010-16 Energy Choice Matters. If you wish to share this story, please
email or post the website link; unauthorized copying, retransmission, or republication
prohibited.
Draft Addresses Proposed Cap On Direct Access Load Within Community Choice Aggregations, Sought By CCA Group
May 6, 2019
Email This Story
Copyright 2010-19 EnergyChoiceMatters.com
Reporting by Paul Ring • ring@energychoicematters.com
NEW Jobs on RetailEnergyJobs.com:
• NEW! -- Retail Energy Operations Analyst
• NEW! -- Retail Energy Operations Specialist
• NEW! -- Account Manager, Energy Choice
• NEW! -- Business Development Manager
|
|
|