|
|
|
|
Texas QSE To Pay $180,000 Under Settlement With Texas PUC Staff
The following story is brought free of charge to readers by EC Infosystems, the exclusive EDI provider of EnergyChoiceMatters.com
Twin Eagle resource
Management, LLC (Twin Eagle) would pay $180,000 under a settlement with Staff of the Public Utility Commission of Texas to resolve alleged violations of 16 Texas Administrative Code (TAC) § 25.503(f) and Electric
Reliability Council of Texas Nodal Protocols §§ 6.4.6, 6.5.7.5, and 6.5.9.3.2.
The settlement states that, "Twin Eagle was the Qualified Scheduling Entity (QSE) for PANDA_T1_CC1,
PANDA_S_CC1, and PANDA_ T2_CC1 when the alleged violations occurred."
The settlement states that, "On November 1, 2017, Twin Eagle relinquished its QSE responsibilities for PANDA_T1_CC1. On March 27, 2019, Twin Eagle relinquished its QSE responsibilities
for PANDA_S_CC1 and PANDA_ T2_CC1."
Under 16 TAC § 25.503(f)(6), a market participant's bids of energy and ancillary services
must be from resources that are available and capable of performing, and shall be feasible
within the limits of the operating characteristics indicated in the resource plan, and
consistent with the applicable ramp rate.
Under ERCOT Nodal Protocols § 6.5.7.5(2),
each QSE is required to operate resources
providing ancillary service capacity to meet its obligations.
The settlement states, "Twin Eagle allocated responsive reserve service (RRS) ancillary service obligations to
PANDA_T1_CC1 on April 19, July 24, August 2, August 4, August 6, and August 10 of
2016. Commission Staff asserts that on these dates, Twin Eagle failed to reserve sufficient
capacity to meet these obligations for 23 separate operating hours. Commission Staff further
asserts that the average capacity shortfall across these operating hours was approximately
seven megawatts. Twin Eagle asserts that the governor for PANDA_T1_CC1 responded out
of accordance with the required dead band settings to low system frequency. Twin Eagle
further asserts this resulted in Twin Eagle intermittently appearing to not reserve or maintain
sufficient capacity to meet these obligations for 23 separate operating hours during these six
days.."
The settlement states, "Twin Eagle allocated RRS ancillary service obligations to PANDA_T2_CC1 on July 14,
July 21, August 3, August 4, August 10, and August 11 of 2016. Commission Staff asserts
that on these dates, Twin Eagle failed to reserve sufficient capacity to meet these obligations for 23 separate operating hours. Commission Staff further asserts that the average capacity
shortfall across these operating hours was approximately eight megawatts. Twin Eagle
asserts that the governor for PANDA_T2_CC1 responded out of accordance with the required
dead band settings to low system frequency. Twin Eagle further asserts this resulted in Twin
Eagle intermittently appearing to not reserve or maintain sufficient capacity to meet these
obligations for 23 separate operating hours during these six days."
Under ERCOT Nodal Protocols § 6.4.6, Twin Eagle is required to provide ERCOT with
accurate telemetry of the current capability of each resource including the resource status,
ramp rates, high sustained limit (HSL), and low sustained limit (LSL).
The settlement states, "Commission Staff asserts from March 11, 2016 through March 31, 2016, Twin Eagle
telemetered inaccurate data to ERCOT relating to the output of PANDA_S_CC1.
Commission Staff asserts the discrepancy between the actual data and the telemetered data
was the result of plant net and plant gross values being transposed."
The settlement states, "Under ERCOT Nodal Protocols § 6.5.9.3.2(3), Twin Eagle is required to notify appropriate
resource units of an ERCOT Advisory under ERCOT."
The settlement states, "On April 19, 2016, ERCOT issued an Advisory at 13:05 because Physical Responsive
Capability had fallen below 3000 megawatts. ERCOT cancelled the Advisory at 18:36 on
the same day."
The settlement states, "Twin Eagle provided email notifications to a number of resource units, as required by
ERCOT Nodal Protocols § 6.5.9.3.2(3). However, Twin Eagle indicates that not all parties
that should have received the notification were included on the email distribution of the
Advisory."
The settlement states, "Twin Eagle neither admits nor denies that any violation occurred."
Docket 49784
ADVERTISEMENT Copyright 2010-16 Energy Choice Matters. If you wish to share this story, please
email or post the website link; unauthorized copying, retransmission, or republication
prohibited.
July 23, 2019
Email This Story
Copyright 2010-19 EnergyChoiceMatters.com
Reporting by Paul Ring • ring@energychoicematters.com
NEW Jobs on RetailEnergyJobs.com:
• NEW! -- Senior Counsel - Regulatory - Retail Supplier
• NEW! -- Sales Representative -- Retail Supplier
• NEW! -- Energy Contracts Counsel -- Retail Supplier
• NEW! -- Senior Natural Gas Energy Trader -- Retail Supplier
• Operations Manager -- Retail Supplier
• Quality Assurance and Customer Service Manager
-- Retail Supplier
|
|
|