Calpine Announces Phase 2 of Powered Land Agreement, Power Supply Agreement to Support Hyperscale Data Center Adjacent to Texas Power Plant
The following story is brought free of charge to readers by VertexOne, the exclusive EDI provider of EnergyChoiceMatters.com
Calpine Corporation today announced the second phase of its 400-megawatt (MW) power supply agreement with Dallas-based CyrusOne, a global data center developer and operator, to serve a new data center adjacent to the Thad Hill Energy Center in Bosque County, Texas.
The new contract adds 210MW of power to the 190MW originally announced in July, completing a deal that will secure power, grid connection, and land to support the CyrusOne facility, which is currently under construction and expected to be operational by the fourth quarter of 2026.
See earlier story on phase I for more background
ADVERTISEMENT Copyright 2025 EnergyChoiceMatters.com. Unauthorized copying, retransmission, or republication
prohibited. You are not permitted to copy any work or text of EnergyChoiceMatters.com without the separate and express written consent of EnergyChoiceMatters.com
November 3, 2025
Email This Story
Copyright 2025 EnergyChoiceMatters.com
Reporting by Paul Ring • ring@energychoicematters.com
NEW Jobs on RetailEnergyJobs.com:
• NEW -- Account Executive (Commercial Retail Energy)
|
|
|
|
|