Generator To Pay $199,000 Under Settlement With Texas PUC Staff
The following story is brought free of charge to readers by VertexOne, the exclusive EDI provider of EnergyChoiceMatters.com
EDP Renewables
North America LLC (EDPR) would pay $199,000 under a settlement with Staff of the Texas PUC to resolve alleged violations of ERCOT Nodal Protocols §§ 3.15(4)(d) and 6.5.7.7(5), related to voltage
support service (VSS).
The settlement states that between February 1, 2023 and May 31, 2023, Mesquite Wind, LLC (Mesquite), Post Oak Wind, LLC (Post Oak),
and Reloj del Sol Wind Farm LLC (RDS), all of which are owned by EDPR, failed to
provide the required VSS, as follows:
a. Mesquite unit LNCRK.UN.G83 was noncompliant for 55 days.
b. Post Oak units LNCRK2.UN.G871 and LNCRK2.UN.G872 were
noncompliant for 35 days.
c. RDS units RELOJ.UN.UNIT1, RELOJ.UN.UNIT2, RELOJ.UN.UNIT3, and
RELOJ.UN.UNIT4 were noncompliant for 109 days.
The settlement states that the EDPR Parties completed integration of
Voltage Support Service (VSS) signaling systems in July 2023
Docket 59411
ADVERTISEMENT Copyright 2026 EnergyChoiceMatters.com. Unauthorized copying, retransmission, or republication
prohibited. You are not permitted to copy any work or text of EnergyChoiceMatters.com without the separate and express written consent of EnergyChoiceMatters.com
February 25, 2026
Email This Story
Copyright 2026 EnergyChoiceMatters.com
Reporting by Paul Ring • ring@energychoicematters.com
NEW Jobs on RetailEnergyJobs.com:
• NEW / Refreshed 2/24/26 -- Manager, ISO Coordination (electricity), Retail Supplier
• NEW -- Billing Analyst - Retail Supplier
• Refreshed 2/2/26 -- Account Executive (Commercial Retail Energy)
|
|
|
|
|