Events

Email Alerts

Retail Energy Jobs

 

 

 

About/Contact

Search

ERCOT IMM: Load Forecast For 60% Increase In Peak, Which Exceeds Supply, "Suggests A Resource Adequacy Constraint Should Be Applied To The Load Interconnection Process"

June 1, 2026

Email This Story
Copyright 2026 EnergyChoiceMatters.com
Reporting by Paul Ring • ring@energychoicematters.com

The following story is brought free of charge to readers by VertexOne, the exclusive EDI provider of EnergyChoiceMatters.com

In a 2025 State of the Market Report, the Independent Market Monitor for ERCOT states that load forecasts showing a 60%+ increase in supply, "suggest[] a resource adequacy constraint should be applied to the load interconnection process so that ERCOT does not approve an amount of new load that is physically infeasible."

This observation by the IMM was not a recommendation from the IMM

Rather, the observation was included in a discussion of load growth, resource adequacy, and direction for future market design

The IMM's report states, "One half of the RA concern is load growth. Having accurate projections of future load growth is critical to interpreting RA calculations. The ERCOT footprint has experienced significant shifts in the past five years with considerable new capacity from wind, solar, and more recently energy storage resources. Project developers have indicated interest in installing a considerable amount of new large load in the form of data centers. The projected load for 2030 (base and adjusted forecast) is between 138 GW and 148 GW with a high scenario value of up to 209 GW. For context, the 138 GW and 148 GW projections reflect increases of 62% to 74% over current peak load over a five year period. There is currently a surplus of capacity in ERCOT for normal weather conditions. However, a 60%+ increase in load cannot be accommodated by current installed capacity. This suggests a resource adequacy constraint should be applied to the load interconnection process so that ERCOT does not approve an amount of new load that is physically infeasible."

Under such a constraint, "Projected load in any year that exceeds feasibility can be deferred, rather than denied interconnection, to allow for generation growth to happen and create room for additional load," the IMM report states

"Significant increase in load that is physically feasible will still result in higher energy and ancillary service prices, which will provide signals for new investment in generation," the IMM report states

The IMM report states that, "Two general approaches to applying a resource adequacy constraint in the load interconnection process are applying real-time operating reserve criteria and applying a multiple of CONE as a market revenue (cost) cap. Both approaches require market simulation some number of years into the future. For the real-time operating reserve constraint, a reliability criteria (e.g. PRC < 3,000 MW) and frequency threshold would need to be determined. The same is true for the market revenue approach (e.g. some multiple of CONE). In either case, simulations would be run depicting various system conditions and the resulting operating reserve levels or market revenue would be viewed to determine the acceptable level of new load for each of the simulated years. Both approaches will allow the market to signal new entry without approving an amount of load that is physically infeasible. New load that cannot be accommodated in one year can be deferred to a later year."

While the IMM noted that discussions among stakeholders have raised the potential for policies requiring new load to either be curtailable or to be subject to a bring-your-own-generation requirement, the IMM expressed concern that, "there may be a limit to the extent the existing natural gas system can accommodate 'bring-your-own-generation' during peak hours."

The IMM stated, "This suggests that a natural gas availability constraint may be appropriate in developing load projections."

The IMM's analysis indicates that the ERCOT market could incorporate more than 3 GWs of new peak demand without the annual frequency of shortage conditions exceeding the norm from 2016 through 2021.

In terms of recommendations, the IMM's report includes only one new recommendation that has not been included in a prior report: Redesign & Improve the Firm Fuel Supply Service (FFSS). Among other changes, the IMM recommends that FFSS eligibility should be limited to resources that can store their fuel onsite or offsite. Additionally, the IMM recommended that FFSS should use a single clearing structure because it provides a single reliability benefit

The IMM continues to express concern with the impact of out-of-market actions, and ERCOT's conservative operations, on the price formation needed in an energy-only market

The IMM reported that, "Despite high operating reserve levels in 2025, out-of-market reliability actions increased substantially from 2024, particularly the Reliability Unit Commitment process."

"ERCOT operators issued RUC instructions for 5,129 resource-hours in 2025, a 176% increase from 2024. Congestion accounted for approximately 77% of these commitments," the IMM said

"The increase in RUC commitments corresponds to higher make-whole payments, which exceeded $21 million in 2025. The increase in make-whole payments can be partially explained by greater use of RUC and fewer resources opting out of RUC settlement. In 2025, only 3% of resources committed through RUC opted out of RUC settlement, compared to 8% in 2024. Thus, most commitments through RUC in 2025 were eligible for make-whole payments," the IMM said

The IMM also said that ERCOT’s demand for ancillary services (AS Methodology), "far exceeds what can be reasonably justified by reliability models."

"The quantities reflected in the AS Demand Curves (ASDC) are misaligned with reasonable reliability criteria and will make it virtually impossible for the market to produce substantial shortage revenues," the IMM said

Concerning the competitiveness of the ERCOT market, the IMM said that the percentage of top-quartile net load hours with a pivotal supplier declined from over 90% in 2022 to 35% in 2025. "This positive development is due in large part to milder weather and a large influx of energy storage resources held by smaller participants," the IMM said

"Despite the positive evidence of competitive conditions in the ERCOT market, we continue to recommend system-wide market power mitigation. With extreme projected load growth in the ERCOT footprint, the market could become structurally uncompetitive during high-load periods within a few years. If even 20 GW of new net load appears, a small fraction of the projected load growth, the operating margin will diminish significantly. This could significantly increase both the frequency of hours with pivotal suppliers and the opportunity to profitably exercise market power. Hence, we recommend that ERCOT begin this process soon to have system-level market power mitigation in place to address the extreme load growth," the IMM said

The IMM's report was filed in Texas PUC Project 34677

ADVERTISEMENT
NEW Jobs on RetailEnergyJobs.com:
Refreshed 5/27/26 -- Manager, ISO Coordination (electricity), Retail Supplier
NEW -- Channel Partner Manager -- Retail Energy

Email This Story

HOME

Copyright 2026 EnergyChoiceMatters.com. Unauthorized copying, retransmission, or republication prohibited. You are not permitted to copy any work or text of EnergyChoiceMatters.com without the separate and express written consent of EnergyChoiceMatters.com

 

Events

Email Alerts

Retail Energy Jobs

 

 

 

About/Contact

Search