|
|
|
|
|
Pa. PUC "Doing Everything Within Our Authority" To Protect Customers & Reliability, As PUC Report Says Modeled Reliability Risk Is Nearly Six Times Worse Than PJM's Planning Standard Due To Data Center Growth
The following story is brought free of charge to readers by VertexOne, the exclusive EDI provider of EnergyChoiceMatters.com
As the Pennsylvania PUC released a report from a consultant indicating that, by 2030, a modeled reliability risk is nearly six times worse than PJM's planning standard due to data center growth, Pennsylvania PUC Chair Steve DeFrank stated, "The PUC will continue doing everything within our authority to protect consumers and reliability, but this issue is bigger than the Commission".
"Pennsylvania's energy system is changing dramatically, and our energy policies need to evolve with it. We need policymakers, regulators, utilities, generators, consumer advocates and other stakeholders working together on a comprehensive approach that encourages economic growth, brings needed energy resources onto the grid, protects existing ratepayers and preserves reliability," DeFrank said
"This analysis sends a clear warning: electricity demand and supply are moving out of balance, and the status quo is not sustainable. We need urgent action at PJM and a broader Pennsylvania energy strategy that makes sure our supply of electricity keeps pace with demand," DeFrank said
The consultant's report stated, in a Reference scenario, which relies on PJM’s 2026 Load Forecast, the
modeled 2030 LOLE [loss of load expectation] is 0.59, or nearly six times worse than the PJM planning
criterion. "This result is mainly due to large-load additions stemming from
data center additions, which are projected to surge in 2030," the report states
In 2030, the
High Load and Low Supply scenario studied by the consultant (a worst-case future of higher-than-expected load additions and constrained resource deployment) has an
LOLE of 13.20.
"This LOLE value is over 100 times worse than PJM’s planning
criterion and indicates an expectation of more than 13 days with loss of
load events per year," the report states
The report did not include any policy recommendations
Link to report
ADVERTISEMENT Copyright 2026 EnergyChoiceMatters.com. Unauthorized copying, retransmission, or republication
prohibited. You are not permitted to copy any work or text of EnergyChoiceMatters.com without the separate and express written consent of EnergyChoiceMatters.com
September 14, 2026
Email This Story
Copyright 2026 EnergyChoiceMatters.com
Reporting by Paul Ring • ring@energychoicematters.com
NEW Jobs on RetailEnergyJobs.com:
• NEW -- Enrollment & Rate Management Director - Retail Supplier
• NEW -- Strategic Sales Channels Manager - Retail Supplier
• NEW -- Controller - Retail Provider
• NEW -- Manager, Product I - VXRetail (Retail Energy)
• Refreshed 5/27/26 -- Manager, ISO Coordination (electricity), Retail Supplier
|
|
|
|
|