Pepco in the District of Columbia sought D.C. PSC approval for two long-term PPAs bundling renewable energy supplies and Tier One RECs which would in aggregate cover 15% of SOS load
Click for More
July 29, 2026
Pepco in the District of Columbia as part of the annual SOS RFP process, has proposed to have PJM Billing Line Item 1935 "be transferred to the utility," relieving SOS suppliers from the charge
Click for More
July 28, 2026
The District of Columbia PSC scheduled for August 18, 2026 a working group to discuss various design elements of electricity standard offer service (SOS), including procurement timing and product type, rate design, and the bypassable SOS adder
Click for More
May 21, 2026
The District of Columbia PSC has directed that an SOS working group shall be convened to discuss recommendations from a PSC-retained consultant concerning the bypassable electricity SOS adder currently used in Pecpo's electricity default service rate
Click for More
May 15, 2026
The District of Columbia PSC will hold a Legislative-Style Hearing on June 3, "to discuss key drivers and possible solutions to the recent increases in the 'generation' portion of a residential customer’s bill," with PSC Commissioner Richard Beverly in a memo describing the hearing as, "an…
Click for More
December 23, 2025
Raises Potential Of Combining SOS Procurements With Other States Considers Alternatives To Full Requirements Contracts, Including Separate Capacity Procurements Changes To Customer Class Groupings Also Raised
With an eye towards affordability and price stability, the District of Columbia PSC has initiated a biennial review of the electricity SOS process
Click for More
November 19, 2025
The District of Columbia PSC approved, with modifications, an RFP to be issued by Pepco to obtain up to an additional 20% of electricity SOS supplies through long-term contracts (which, if resulting in successful bids, could bring the total amount of SOS under long-term contracts to 25%)
Click for More
October 16, 2025
"[T]he issue of exposing SOS customers to PJM capacity prices -- without hedging at least part of that exposure -- warrants further inquiry," the District of Columbia Government (DCG or the District), through the Office of the Attorney General and Department of Energy and Environment (DOEE), said in…
Click for More
October 1, 2025
The District of Columbia PSC has directed that a higher capacity proxy price be used in Pepco's 2025-2026 RFP for electricity SOS supplies
Click for More
August 15, 2025
The District of Columbia PSC, in a 2-1 decision, directed Pepco to attempt to procure a target quantity of 25% of SOS load through renewable energy power purchase agreements.
Click for More
July 14, 2025
Pepco in the District of Columbia has sought approval of an agreement for a bundled procurement of renewable energy and Tier One renewable energy credits from a solar facility, to serve approximately 7% of total SOS load
Click for More
June 4, 2025
Pepco in the District of Columbia has sought clarification from the D.C. PSC concerning which Community Renewable Energy Facilities (CREF) costs may be included in the bypassable SOS administrative charge
Click for More
May 20, 2025
Consumer Counsel Supports Recommendation That SOS Admin. Charge Be Tied To Or Verified Against Competitive Third-Party Supply Pricing, To Ensure Adder Does Not Undercut Competition
Click for More
April 15, 2025
A consultant retained by Pepco, at the direction of the District of Columbia PSC, to conduct an audit of the bypassable SOS Admin. Charge, has recommended that the current bypassable Adder included in the bypassable SOS Admin. Charge at Pepco should be, "tied more closely to competitive third-party…
Click for More
February 11, 2025
District of Columbia PSC Commissioner Richard Beverly has directed stakeholders to provide their updated position on the amount of electricity SOS load that should be served under a long-term PPA
Click for More
May 2, 2024
A PSC has ordered an EDC to remove from the bypassable SOS administrative charge certain costs
Click for More
April 2, 2024
The District of Columbia PSC has again affirmed that the long-term renewable energy PPA to be procured by Pepco for SOS customers shall not exceed 5% of SOS load
Click for More
October 27, 2023
A PSC directed that…
Click for More
August 7, 2023
The District of Columbia PSC has opened biennial review of electricity Standard Offer Service
Click for More
June 6, 2023
In comments on potential changes to the provisions governing the use of a long-term renewable energy contract for a portion of SOS load in the District of Columbia, the D.C. Office of People's Counsel suggested that the RFP for such renewable energy be opened to, "third-party suppliers".
Click for More
April 21, 2023
Pepco in the District of Columbia sought flexibility to increase the amount of SOS load to be served under a long-term renewable energy contract, after a previously executed contract for 5% of SOS load has been terminated by the renewable developer
Click for More
May 22, 2020
Pepco has filed with the District of Columbia PSC a draft RFP to solicit long-term contracts for renewable energy and attributes to serve 5% of SOS load
Click for More
April 10, 2020
Sets Margin For SOS Provider PSC Expects To Expand Percentage Of SOS Served Under Long-Term Contracts, If Risks Can Be Minimized
The District of Columbia PSC has adopted a model and cost recovery mechanism for integrating a long-term renewable energy power purchase agreement (PPA) for a target quantity of five (5) percent of the Standard Offer Service (SOS) load into the SOS portfolio.
Click for More
October 28, 2019
The District of Columbia PSC has adopted compliance tariffs from Pepco to implement the previously ordered elimination of the 12-month minimum stay on SOS for commercial customers who return to SOS after taking competitive supply.