February 23, 2015
FERC Allows PJM to Retain Capacity Otherwise Due To Be Released, But Rejects (Without Prejudice) Additional Non-RPM Capacity Procurements
FERC approved PJM's request to retain 2,000 MW of capacity that would otherwise be released under the RPM incremental project, but denied a separate request from PJM for authorization to enter into contracts for capacity for reliability purposes outside of the centralized capacity market.