May 16, 2025
NJ Gov. Directs BPU To Open Proceeding On Resource Adequacy
Public Service Electric and Gas Company's (PSE&G) proposal for residential electric bill cost mitigation, due to increases in the New Jersey electric Basic Generation Service rates, would provide relief to customers through distribution-side bill credits applied to all residential customer bills…
Click for More
May 9, 2025
In a summer outlook, PJM said today that under an extreme summer 2025 planning scenario, PJM forecasts that available generation capacity may fall short of the required reserves
Click for More
February 17, 2025
ENGIE Flexible Generation NA LLC has filed at the Texas PUC to withdraw its Perseus generation project from the PUC's Texas Energy Fund (TEF) In-ERCOT Loan Program
Click for More
February 13, 2025
ERCOT has posted its December 2024 CDR, which is the first to include, in the primary forecast, new forecasted loads reported by Transmission Service Providers for expected loads that do not have a signed interconnection agreement (mostly large loads) and which would otherwise not have been included…
Click for More
February 3, 2025
ERCOT said in a market notice that February 10, 2025 is the "target" posting week for the 2024 final Report on Capacity, Demand and Reserves (CDR).
Click for More
January 28, 2025
ERCOT is canceling the Request for Proposal for Must-Run Alternatives to the use of certain of CenterPoint Energy Houston Electric's mobile generation (Life Cycle Power Mobile Generation Solution) as an alternative to an RMR agreement for CPS Energy's Braunig Units 1 & 2
Click for More
December 23, 2024
ERCOT has issued another RFP seeking Must-Run Alternative (MRA) Resources in lieu of executing a Reliability Must Run (RMR) agreement with CPS Energy Braunig Units 1 and/or 2
Click for More
December 19, 2024
"CenterPoint Energy (CNP)" said today in a news release that
Click for More
December 17, 2024
Vistra today announced that…
Click for More
December 16, 2024
ERCOT said in a market notice that the posting of the 2024 final Report on Capacity, Demand and Reserves (CDR) is being delayed from December 20, 2024, to…
Click for More
December 13, 2024
In a "final recommendation", Staff of the Texas PUC formally filed comments in Project 55000 recommending that…
Click for More
December 12, 2024
While the Texas PUC did not at today's open meeting, adopt decisions regarding the performance credit mechanism (PCM) or ancillary service design or quantities, a majority of Commissioners did express a view that…
Click for More
December 12, 2024
A new Texas bill has been pre-filed that would require the Texas PUC to…
Click for More
December 12, 2024
The Texas PUC has advanced to a due diligence round a second project from NRG Energy representing proposed new generation to be built in ERCOT under the PUC's Texas Energy Fund (TEF) In-ERCOT Loan Program
Click for More
December 6, 2024
IMM: "PCM Revenues Will Not Likely Be As Efficient As Shortage Pricing In Motivating Investment In Resources That Provide The Highest Reliability Value" ERCOT Report: PCM With Cost Cap Would Not Incentivize Sufficient Generation
The ERCOT Independent Market Monitor filed with the Texas PUC an assessment of Performance Credit Mechanism (PCM)
Click for More
December 3, 2024
Baltimore Gas & Electric, Pepco-Maryland, and Delmarva-Maryland have no "firm plans" to build generation in Maryland, but…
Click for More
November 22, 2024
As one of the means to address resource adequacy concerns, a PSC should consider requiring wholesale default service electricity suppliers to bilaterally procure capacity from smart thermostat customers and distributed energy resources, NRG says
Click for More
November 21, 2024
ERCOT reported at today's Texas PUC opening meeting that it is working on developing an agreement to move the mobile generation units of CenterPoint Energy Houston Electric from Houston to the San Antonio area, as an alternative to entering into reliability must-run agreements with two CPS Energy units which will suspend operations
Click for More
November 15, 2024
The Pennsylvania PUC formally announced that it will hold a Technical Conference regarding resource adequacy
Click for More
November 11, 2024
Staff of the Maryland PSC have offered an overview of resource adequacy policies and options available to the Maryland PSC
Click for More
November 1, 2024
During an earnings call today…
Click for More
October 17, 2024
A sponsor of a Texas generation project filed…
Click for More
October 10, 2024
Hoping to, "better wield control of clean resource development," within…
Click for More
August 29, 2024
The Texas PUC has advanced to a due diligence review over 4,100 MW of proposed new generation to be built in ERCOT by affiliates of Texas retail electric providers
Click for More
August 22, 2024
ERCOT in a filing with the Texas PUC recommends that the value of lost load, for purposes of planning activities including the reliability standard, be set at…
Click for More