November 4, 2014
Baltimore Gas & Electric has posted on its website a new weighted average SOS rate for the period Oct. 1, 2014 through Sep. 30, 2015, which includes the summer SOS rate for 2015.
Click for More
October 6, 2014
AEP Ohio has petitioned the Public Utilities Commission of Ohio to expand a previously proposed nonbypassable surcharge to support entitlements AEP Ohio would retain in the Ohio Valley Electric Corporation (OVEC) to now include PPAs with several additional competitive AEP generating resources…
Click for More
October 3, 2014
The Pennsylvania PUC has issued a formal rulemaking proposal containing revised regulations governing interest rates applicable to electric default service over-collections and under-collections.
Click for More
September 30, 2014
PPL's Price to Compare will increase on October 1 due to changes in the transmission rate component of the price.
Click for More
September 29, 2014
A segment of Ohio industrial customers has voiced support for Duke Energy Ohio's proposed Price Stabilization Rider, while at the same time proposing that very large customers (and only those customers) be permitted to make an election to avoid the rider.
Click for More
August 5, 2014
As part of their electric security plan for the period beginning June 1, 2016, the FirstEnergy Ohio utilities have proposed implementing 15-year ratepayer backed contracts to support two power plants owned by FirstEnergy Solutions (as well as its share in a jointly owned plant) under an "Economic…
Click for More
August 5, 2014
The FirstEnergy Ohio utilities would continue to rely on a mix of 12, 24, and 36-month contracts to serve all default service classes under an electric security plan covering the period June 1, 2016 to May 31, 2019
Click for More
July 28, 2014
AEP updated investors during its Friday earnings call on its approach to its unregulated generation business.
Click for More
July 24, 2014
AEP Ohio's sought Power Purchase Agreement Rider amounts to "reregulating" the company's generation, reversing the course of prior PUCO orders, Public Utility Commission of Ohio Staff said in a post-hearing brief in AEP Ohio's electric security plan proceeding.
Click for More
July 24, 2014
Sharyland Utilities, LP has filed to implement Transmission Cost Recovery Factor rates, applicable to retail electric providers, for customers with interval data recorder (IDR) meters.
Click for More
July 3, 2014
CenterPoint Energy Houston Electric has filed at the Public Utility Commission of Texas to set Rider RCE - Rate Case Expenses Surcharge to zero, as rider has collected all of the necessary expenses.
Click for More
June 17, 2014
PSNH has filed to increase its energy service (default service) electric rate effective July 1; however, the rate is slightly lower than its preliminary estimate of the July rate adjustment filed in May.
Click for More
May 30, 2014
Duke Energy Ohio has filed for approval of an electric security plan governing the procurement and pricing of default service for the period June 1, 2015 to May 31, 2018
Click for More
May 29, 2014
The Public Utilities Commission of Ohio has approved implementation of a nonbypassable rider for certain deferred generation costs at Dayton Power & Light, but denied making additional deferred transmission costs nonbypassable.
Click for More
May 23, 2014
The Pennsylvania PUC approved nonbypassable charges at Citizens' Electric Co. and Wellsboro Electric Co. to recover unanticipated and excessive costs from the polar vortex.
Click for More
May 23, 2014
The Pennsylvania PUC issued an advanced notice of proposed rulemaking to implement a uniform interest rate applicable to over- and under-collections of electric default service costs via reconciliation of automatic adjustment clauses.
Click for More
May 22, 2014
The Illinois Commerce Commission has opened an investigation into Commonwealth Edison's current rate design which provides generation supply rate subsidies to non-residential space heat and lighting customers (Docket 14-0385).
Click for More
May 21, 2014
Staff of the Public Utilities Commission of Ohio have proposed that the Commission reject AEP Ohio's proposed Power Purchase Agreement Rider, in testimony on AEP Ohio's electric security plan filing.
Click for More
May 21, 2014
Staff of the Public Utilities Commission of Ohio have recommended "significant" changes to AEP Ohio's proposed purchase of receivables program, in testimony filed in AEP Ohio's electric security plan proceeding.
Click for More
May 2, 2014
Dayton Power & Light has filed to implement a nonbypassable rider for certain generation supply costs, under a "circuit breaker" provision for certain reconciled default service costs.
Click for More
April 28, 2014
The New York PSC has approved a mechanism for Niagara Mohawk to recover mitigated default electric service costs from February.
Click for More
April 28, 2014
AEP sees an opportunity for long-term contracts to provide rate stability to Ohio customers while supporting existing generation.
Click for More
April 16, 2014
A settlement among Citizens' Electric Company of Lewisburg, PA, Wellsboro Electric Company, the Office of Consumer Advocate and the Office of Small Business Advocate would institute a nonbypassable rider, up to 1¢/kWh, to recover generation costs from the polar vortex.
Click for More
March 31, 2014
Commonwealth Edison has proposed to change how the Purchased Electricity Adjustment (PEA) is applied.
Click for More
March 20, 2014
The Public Utilities Commission of Ohio has approved an alternative proposal from AEP Ohio to mitigate the impact of the transition to market-based rates on residential customers at Columbus Southern Power (CSP).
Click for More