Maryland PSC Staff Propose Reporting Requirements for Curtailment Service Providers

Email This Story

Copyright 2012 EnergyChoiceMatters.com.

Maryland PSC Staff has proposed annual reporting requirements for curtailment service providers, which are subject to licensure by the Commission.

The Commission previously noted that curtailment service providers possess information that could assist the Commission in its statutory obligation to plan for and report on resource adequacy, and inform the Commission regarding the type and amount demand response resources in Maryland, and directed Staff to determine what information should be filed.

Working with stakeholders, Staff believes that the information required by the Commission is already contained in reports curtailment service providers must file with the Maryland Department of the Environment per COMAR 26.11.36.04, and recommended that the PSC find that these reports will meet the PSC's informational needs.

The information required by COMAR 26.11.36.04 is outlined below:

A CSP that administers a demand response program for a participating facility in the State shall provide the following information to the Department in an annual report:

(1) The name and address of each participating facility and the telephone number and name of a contact person;

(2) The identification of each participating engine at the facility, including:

(a) The registration number assigned by the Department for each engine and its rated capacity in horsepower and kilowatts;

(b) The manufacturer and model

(c) The installation date;

(d) The type of fuel used in each engine;

(e) A copy of or the mail log number associated with The Public Service Commission of Maryland Certificate of Public Convenience and Necessity (CPCN) Exemption, pursuant to Public Utility Companies Article, §7-207.1, Annotated Code of Maryland, as applicable, including unit type of generator, for example, Type I Generator, Type II Generator; and

(f) The PJM Interconnection, LLC utility zone for the participating facility;

(3) A description of the demand response program for each participating engine, that is, whether it is an economic response program or an emergency response program;

(4) As called for by the CSP, the dates on which each engine was requested to operate during the year and the hours of operation on each date, including:

(a) The reason for operating the engine under a demand response program, that is, whether it is an economic response program or an emergency response program;

(b) The starting and ending times when each engine was requested to operate as called for by the CSP; and

(c) The total kilowatt-hours of generation during each demand response operation;

(5) A list of curtailment activities at each participating facility, the total hours and the total kilowatt hours of generation curtailment as called for by the CSP;

(6) A brief description of any significant increase or decrease in the total hours of demand response operation compared to total operation during the previous year; and

(7) An attestation from the CSP that the CSP has:

(a) Attempted to collect the required information from each participating facility or other appropriate source; and

(b) Provided information that is true and correct to the best of their knowledge and is not misleading.

You can follow specific tags with a free account and see their newest stories in one place. Sign up or sign in.

Copyright 2012 EnergyChoiceMatters.com. Unauthorized copying, retransmission, or republication prohibited. You are not permitted to copy any work or text of EnergyChoiceMatters.com without the separate and express written consent of EnergyChoiceMatters.com.

Energy Search PartnersEnd of Story BannerBefore NewNow 728 × 90New slot. Directly under the article text, at peak attention.

More News

Maryland PSC Staff Propose Reporting Requirements for Curtailment Service Providers | EnergyChoiceMatters.com