Calpine to Build New Capacity in ERCOT for Summer 2014

Email This Story

Copyright 2012 EnergyChoiceMatters.com.

Calpine announced Friday that it is actively permitting the addition of 520 MW of combined-cycle capacity at existing sites in ERCOT, with anticipated commencement of commercial operations by the summer of 2014.

Specifically, Calpine is moving forward with 260 MW expansions at both its Deer Park and Channel Energy centers.

The capacity comes from both the installation of an additional combustion turbine at each site, plus an improvement in the efficiency of the existing turbines.

The 260 MW represents incremental baseload capacity at annual average conditions. Incremental summer peaking capacity is approximately 200 MW per unit, supplemented by incremental efficiencies across the balance of the plant.

Excluding the benefits of the increased efficiencies, Calpine said that the new capacity will be added at an overnight cost of less than $550/kW.

You can follow specific tags with a free account and see their newest stories in one place. Sign up or sign in.

Copyright 2012 EnergyChoiceMatters.com. Unauthorized copying, retransmission, or republication prohibited. You are not permitted to copy any work or text of EnergyChoiceMatters.com without the separate and express written consent of EnergyChoiceMatters.com.

Energy Search PartnersEnd of Story BannerBefore NewNow 728 × 90New slot. Directly under the article text, at peak attention.

More News

Calpine to Build New Capacity in ERCOT for Summer 2014 | EnergyChoiceMatters.com