HomeJanuary 18, 2013

New York Orders National Grid, NYSEG to Investigate Repowering Generating Plants

Email This Story

Copyright 2013 EnergyChoiceMatters.com.

The New York State Public Service Commission yesterday instituted a proceeding, "to examine repowering alternatives to utility power plant reinforcements," and directed National Grid and New York State Electric and Gas Corporation (NYSEG) to work with generation owners to evaluate repowering of two power plants in upstate New York.

An order initiating the proceeding was not immediately available.

According to a press release, the Commission directed National Grid to evaluate repowering as an alternative outcome for the Dunkirk generating station and NYSEG to do the same for the Cayuga generating stations. "The closing of the power plants could cause reliability concerns. The companies will examine the relative costs and benefits of repowering the plants at their existing sites compared to alternative transmission upgrades over the long term," the PSC said.

To the extent utilities become involved in the repowering of generation, it raises issues concerning the allocation costs as well as the disposition of any power and other products from the plants, including the treatment of ESCO and default service customers. The PSC's press release did not address such issues.

"The benefits to be evaluated include the reliability, environmental, and customer impacts associated with the repowering and transmission solutions," the PSC said.

As part of this evaluation, the companies will file with Department of Public Service Staff projected costs of the transmission alternatives that they propose to evaluate, solicit bids from the current owners of the Dunkirk and Cayuga plants for the level of support required to finance repowering of their respective facilities, and file reports analyzing repowering alternatives in terms of reliability and other impacts and make recommendations to the Commission.

The coal-fired Dunkirk generating station located in Chautauqua County, New York, consists of four units with combined nameplate rating of over 635 megawatts (MW). Units 1 and 2 are each rated at 100 MW and Units 3 and 4 are each rated 217.6 MW.

The Cayuga facility located in Lansing, New York, consists of two coal-fired units with a combined capacity of over 312 MW. Unit 1 has a net capacity rating of 154 MW and Unit 2 of 158.7 MW.

"Evaluating repowering is consistent with the New York Energy Highway Task Force Blueprint which cited the potential benefits of repowering and recommends that electric utilities be required to analyze repowering as an alternative to transmission system upgrades when a facility needed for reliability proposes to retire," said PSC Chairman Garry Brown.

Case 12-E-0577

You can follow specific tags with a free account and see their newest stories in one place. Sign up or sign in.

Copyright 2013 EnergyChoiceMatters.com. Unauthorized copying, retransmission, or republication prohibited. You are not permitted to copy any work or text of EnergyChoiceMatters.com without the separate and express written consent of EnergyChoiceMatters.com.

Energy Search PartnersEnd of Story BannerBefore NewNow 728 × 90New slot. Directly under the article text, at peak attention.

More News

New York Orders National Grid, NYSEG to Investigate Repowering Generating Plants | EnergyChoiceMatters.com