HomeMay 6, 2013
Baltimore Gas & Electric Files New SOS Rates, Updates Transmission, Rider 8
Copyright 2013 EnergyChoiceMatters.com.
Baltimore Gas & Electric has filed with the Maryland PSC new SOS rates for the period October 1, 2013 to May 31, 2014 for residential and Type I customers, and the period June 1, 2013 to August 31, 2013 for Type II customers.
The BGE generation rate, excluding transmission and Rider 8 (reconciliation) will be as follows, in cents per kWh:
Schedule R, 10/1/13 - 5/31/14 8.924 Schedule RL, 10/1/13 - 5/31/14 On-Peak 11.014 Inter.-Peak 9.884 Off-Peak 7.624 Scheds. G/GU - Type I SOS, 10/1/13 - 5/31/14 8.101 Sched. GS - Type I SOS, 10/1/13 - 5/31/14 On-Peak 9.961 Inter.-Peak 8.942 Off-Peak 6.974 Sched. G - Type II SOS, 6/1/13 - 8/31/13 9.181 Sched. GS - Type II SOS, 6/1/13 - 8/31/13 On-Peak 13.322 Inter.-Peak 8.290 Off-Peak 6.709 Scheds. GL, P & T - Type II SOS, 6/1/13 - 8/31/13 On-Peak 12.849 Inter.-Peak 7.932 Off-Peak 6.656
Rates for additional classes can be found in BGE's filing (click here). The same filing includes updated bypassable transmission rates. BGE has also updated bypassable Rider 8, the reconciliation factor; new Rider 8 amounts can be found here.
You can follow specific tags with a free account and see their newest stories in one place. Sign up or sign in.
Copyright 2013 EnergyChoiceMatters.com. Unauthorized copying, retransmission, or republication prohibited. You are not permitted to copy any work or text of EnergyChoiceMatters.com without the separate and express written consent of EnergyChoiceMatters.com.