Potomac Edison Files New SOS Rates
Copyright 2016 EnergyChoiceMatters.com.
Potomac Edison has filed with the Maryland PSC new SOS rates for residential and Type I customers for the period beginning June 1, 2016, and the period beginning March 1, 2016 for Type II customers
The summer 2016 Schedule R residential electric supply charge at Potomac Edison is about 15% lower than the comparable summer 2015 charge.
Unless otherwise indicated for capacity charges, rates below are in cents per kWh. Rates reflect only the energy (and capacity where applicable) component of SOS, and not transmission or reconciliations.
Potomac Edison SOS Energy Rates Schedule R (Residential) June 1, 2016 - September 30, 2016 Electric Supply Charge: 6.019 October 1, 2016 - May 31, 2017 Electric Supply Charge: 6.067 Schedule C (General & Commercial), Type I June 1, 2016 - September 30, 2016 Electric Supply Charge: First Block (0-350 kWh): 9.873 Second Block (next 350 kWh): 9.692 Third Block (Over 700 kWh): 3.796 October 1, 2016 - May 31, 2017 Electric Supply Charge: First Block (0-350 kWh): 9.787 Second Block (next 350 kWh): 9.592 Third Block (Over 700 kWh): 3.762 Schedule C (General & Commercial), Type II Electric Supply Charges Mar. 1, 2016 - May 31, 2016 First Block (0-350 kWh): 9.790 Second Block (next 350 kWh): 9.601 Third Block (Over 700 kWh): 3.761 Schedule G (General Service), Type I June 1, 2016 - September 30, 2016 Capacity Charge All kW in excess of 7.5 kW: $6.24/kW Energy Charge First Block (0-700 kWh): 8.195 Second Block (over 700 kWh): 3.794 October 1, 2016 - May 31, 2017 Capacity Charge All kW in excess of 7.5 kW: $6.17/kW Energy Charge First Block (0-700 kWh): 8.124 Second Block (over 700 kWh): 3.760 Schedule G (General Service), Type II Mar. 1, 2016 - May 31, 2016 Capacity Charge All kW in excess of 7.5 kW: $6.18/kW Energy Charge First Block (0-700 kWh): 8.119 Second Block (over 700 kWh): 3.759 Schedule C-A (General Service - All Electric), Type I Electric Supply Charges June 1, 2016 - September 30, 2016 First Block (0-350 kWh): 10.927 Second Block (next 350 kWh): 9.507 Third Block (over 700 kWh): 5.005 October 1, 2016 - May 31, 2017 First Block (0-350 kWh): 10.824 Second Block (next 350 kWh): 9.418 Third Block (over 700 kWh): 4.957 Schedule C-A (General Service - All Electric), Type II Electric Supply Charges Mar. 1, 2016 - May 31, 2016 First Block (0-350 kWh): 10.823 Second Block (next 350 kWh): 9.413 Third Block (over 700 kWh): 4.960 Schedule C-A (General Service - All Electric, School/Church Space Heating Subclass), Type I June 1, 2016 - September 30, 2016 Electric Supply Charge (all kWh): 5.772 October 1, 2016 - May 31, 2017 Electric Supply Charge (all kWh): 5.717 Schedule C-A (General Service - All Electric, School/Church Space Heating Subclass), Type II Mar. 1, 2016 - May 31, 2016 Electric Supply Charge (all kWh): 5.720 Schedule PH (Light & Power), Type II Mar. 1, 2016 - May 31, 2016 Capacity Charge First Block (0-500 kW): $11.63/kW Second Block (over 500 kW): $11.33/kW Energy Charge First Block (0-100,000 kWh): 2.615 Second Block (over 100,000 kWh): 2.366
Rates for additional lighting classes can be found in Potomac Edison's filing (click here)