ECM, Energy Choice Matters

Informing the Industry on What Truly Matters
in Retail Energy

Sign InRegister

HomeSeptember 30, 2022

Texas PUC Staff Seek Stakeholder Comment On Interconnections Between ERCOT, Other Grids; Issue Questions

Email This Story

Copyright 2022 EnergyChoiceMatters.com.

The following story is brought free of charge to readers by EC Infosystems, the exclusive EDI provider of EnergyChoiceMatters.com

Staff of the Texas PUC have issued a request for stakeholder comment on several questions related to interconnections between ERCOT and other grids

In 2021, the Texas Legislature passed Senate Bill (SB) 1, 87th Regular Session, which required the Commission to detail in the Biennial Report required under Sec. 12.203, Utilities Code, whether Electric Reliability Council of Texas (ERCOT) interconnection to Eastern and/or Western Interconnects and/or Mexico would protect and further the interest of the public. The Commission is required to submit its Biennial Report to the Texas Legislature by no later than January 15, 2023.

Commission Staff seeks public comment on the following five questions:

(1) the utilization of current direct current ties between ERCOT and other interconnects, including reliability benefits provided and costs;

(2) the potential of expanded direct current ties between ERCOT and other interconnection, including reliability benefits, costs, and economic development benefits;

(3) the potential of establishing alternating current ties between ERCOT and other interconnects for specific reliability purposes;

(4) the impact of any additional interconnections on ERCOT's ability to remain independent of federal regulation; and

(5) any other relevant information that commenters believe is neces

Project 54163

You can follow specific tags with a free account and see their newest stories in one place. Sign up or sign in.

Copyright 2022 EnergyChoiceMatters.com. Unauthorized copying, retransmission, or republication prohibited. You are not permitted to copy any work or text of EnergyChoiceMatters.com without the separate and express written consent of EnergyChoiceMatters.com.

Energy Search PartnersEnd of Story BannerBefore NewNow 728 × 90New slot. Directly under the article text, at peak attention.

More News

Texas PUC Staff Seek Stakeholder Comment On Interconnections Between ERCOT, Other Grids; Issue Questions | EnergyChoiceMatters.com