ECM, Energy Choice Matters

Informing the Industry on What Truly Matters
in Retail Energy

Sign InRegister

HomeJanuary 5, 2016

Texas Generator Would Pay $40,000 Under Settlement With PUCT Staff

Email This Story

Copyright 2016 EnergyChoiceMatters.com.

Austin Energy would pay $40,000 under a settlement with Staff of the Public Utility Commission of Texas to resolve an investigation into Austin Energy's alleged failure to adhere to Electric Reliability Council of Texas (ERCOT) Protocols § 8.5.1.1, relating to governor in service; and, ERCOT Operating Guide §§ 2.2.8 and 2.3.1.2, relating to primary frequency response (PFR).

Commission Staff alleged that Austin Energy resource SANDHSYD_CC1 failed to provide adequate PFR during 13 of 20 measureable events during a 2011-12 study period and alleged that, during the study period, four failures occurred while SANDHSYD_CC1 was providing Responsive Reserve (RRS) and was therefore required to reserve capacity to provide PFR.

Commission Staff alleged that Austin Energy resource DECKER_DPG2 failed to provide adequate PFR during 1 of 8 measureable events during a 2011-12 study period and that, during the study period, one failure occurred while DECKER_DPG2 was providing RRS and was therefore required to reserve capacity to provide PFR.

Docket 45493

You can follow specific tags with a free account and see their newest stories in one place. Sign up or sign in.

Copyright 2016 EnergyChoiceMatters.com. Unauthorized copying, retransmission, or republication prohibited. You are not permitted to copy any work or text of EnergyChoiceMatters.com without the separate and express written consent of EnergyChoiceMatters.com.

Energy Search PartnersEnd of Story BannerBefore NewNow 728 × 90New slot. Directly under the article text, at peak attention.

More News

Texas Generator Would Pay $40,000 Under Settlement With PUCT Staff | EnergyChoiceMatters.com