HomeOctober 9, 2026
PSC Corrects Erroneous SOS Proxy Price Directive
Copyright 2026 EnergyChoiceMatters.com.
The following story is brought free of charge to readers by VertexOne, the exclusive EDI provider of EnergyChoiceMatters.com
The District of Columbia PSC issued an errata concerning its approval of an updated Wholesale Full Requirements Service Agreement (WFRSA) for the 2026-2027 SOS solicitations at Pepco-DC
As first reported by EnergyChoiceMatters.com on October 7, the PSC in its order set the PJM capacity proxy price used in SOS bidding, where applicable, at $325.00/MW-day, rather than the average price of the prior two BRA auctions or $329.35/MW-day, consistent with the methodology employed last year.
However, the PSC in doing so did refer to the use of the $325.00/MW-day proxy price as being for the 2027/28 and 2028/29 delivery years, for which a PJM base residual auction capacity price exists
The PSC said that such direction regarding a proxy price for the 2027/28 and 2028/29 delivery years was in error, and struck such direction from its order
The use of a proxy price of $325.00/MW-day for the 2029/30 delivery year remains in place
FC 1017
You can follow specific tags with a free account and see their newest stories in one place. Sign up or sign in.
Copyright 2026 EnergyChoiceMatters.com. Unauthorized copying, retransmission, or republication prohibited. You are not permitted to copy any work or text of EnergyChoiceMatters.com without the separate and express written consent of EnergyChoiceMatters.com.